Schedule update is about integrity of forecasts!
P6 schedule update is not a data entry exercise, it is a technical process that protects the "integrity of the baseline and forecast". A defensible P6 schedule update begins with controlling the data date, percent complete type, and calendar assignments before any progress is entered. Actual start and finish dates must align with approved field progress, while remaining durations should reflect realistic productivity, not automatic software recalculation. Logic must be prese